Sequencing activities in a project network using resource complementarity model

Author(s): Silva, Hélder C. cv logo 1 ; Tereso, Anabela Pereira cv logo 2 ; Oliveira, José A. cv logo 3

Date: 2012

Persistent ID: http://hdl.handle.net/1822/21590

Origin: RepositóriUM - Universidade do Minho

Subject(s): Project Management; Scheduling; Complementarity of Resources; Operational Research


Description
The methodology of project management has been widespread in organizations of different functions and sizes. In this context, we address the issue of optimal resource allocation, and more specifically, the analysis of complementarity of resources (primary resource and supportive resource) in a project. We develop a conceptual system capable of determining the ideal timing, and the ideal mixture of resources allocated to the activities of a project, such that the project is completed on time, if not earlier, with minimal cost. In this paper we present new computational results of a Genetic Algorithm, based in a random keys alphabet to optimize the process to reach better results.
Document Type Conference Object
Language English
delicious logo  facebook logo  linkedin logo  twitter logo 
degois logo
mendeley logo

Related documents



    Financiadores do RCAAP

Fundação para a Ciência e a Tecnologia Universidade do Minho   Governo Português Ministério da Educação e Ciência Programa Operacional da Sociedade do Conhecimento EU